Upcoming Digging Project? Whether you’re planting a tree, installing a fence or starting a construction project, a free utility locate helps prevent outages, injuries and costly repairs.

Here’s some worry-free steps to safe digging:


CALL 811 – It’s FREE & EASY!

Dial 811 or submit a request online at least two (2) business days before the start of any digging project. 

FOR HOMEOWNERS:

Request a ticket

FOR EXCAVATORS/PROFESSIONALS:

Submit a Request

MARK YOUR WORK ZONE

Designate your proposed work area with WHITE paint or flags.

WAIT

Allow 48 business hours for the utility companies to locate and mark lines in the work area. Verify all affected utility companies have responded by matching markings listed on your 811 ticket. 

TIP: Refer to KNOW THE MARKS (see below)


RESPECT

Preserve all markings (flags/paint) provided by the utility companies. These markings are your guide for the duration of the project.

CAREFULLY DIG

Maintain an 18” buffer on each side of marked lines and dig with care. 

TIP: In Texas, the accepted safety margin or tolerance zone is 18 inches on each side of the marked utility line.


KNOW THE MARKS

White – Proposed Excavation

Pink – Temporary Survey Markings

Blue – Potable Water

Green – Sewer & Drain Lines

Purple – Irrigation & Slurry Lines, Reclaimed Water

Red – Electrical Power Lines, Cable, Conduit & Lighting Cables

Yellow – Gas, Oil, Steam, Petroleum or Gaseous Materials

Orange – Communications, Alarm or Signal Lines, Cable or Conduits

Before you dig, know what’s below.